What small modular reactors are, how passive safety works, which designs the NRC has approved and when, and the cost and fuel hurdles still facing SMRs.

Small modular reactors (SMRs) are nuclear fission reactors that produce up to about 300 megawatts of electricity (MWe) per unit, roughly a third of a traditional large reactor, with components designed to be built in a factory and shipped to the site as modules [1]. The pitch is cheaper, faster, more flexible nuclear power. As of November 2026, U.S. regulators have certified or approved two SMR designs and issued a construction permit for one SMR project, but no commercial SMR is operating in the United States [5][6][8].

What makes a reactor "small" and "modular"

Each word in the name does a job.

  • Small. The International Atomic Energy Agency's Advanced Reactors Information System (ARIS) describes SMRs as advanced reactors with a capacity "typically up to 300 MW(e) per unit," about one-third of conventional reactors [1]. The U.S. Department of Energy (DOE) puts the range at "tens of megawatts up to hundreds of megawatts" [2].
  • Modular. Components and systems "can be shop fabricated and then transported as modules to the sites for installation as demand arises" [1]. DOE says SMR parts will be factory-made and shipped, which should make them quicker and less costly to build [3].
  • Reactor. The physics is ordinary fission. Uranium atoms split, releasing heat, which boils water or heats another coolant to drive a turbine.

Below SMRs sit microreactors. The IAEA ARIS booklet describes them as a subcategory with electrical output typically up to about 10 MWe [1]. DOE says most microreactor designs produce 1 to 20 megawatts of thermal energy and are small enough to move by truck, ship, aircraft or rail [4].

A useful analogy is aircraft versus ships. Large reactors are like ocean liners, each one essentially custom-built in a shipyard over many years. SMRs aim to be more like airliners: one certified design, built repeatedly on a production line, with savings coming from volume rather than size.

How SMRs work

The basic loop

Most near-term SMRs are scaled-down versions of the light-water reactors that already supply nuclear power in the U.S. Fission heats water in the core; the heat makes steam, directly or through a heat exchanger; the steam spins a turbine generator. NuScale's certified design, for example, rates each module at 160 megawatts thermal and 50 MWe [5].

Passive safety

The main engineering change is how SMRs stay safe when something goes wrong. Large older plants rely heavily on powered pumps and backup diesel generators to keep cooling water flowing after a shutdown. Many SMRs use physics instead.

The NRC's final rule certifying NuScale's design states that "NuScale has no safety-related functions that rely on electrical power" and that the design needs no pumps to inject water into the core after an accident [5]. The NRC says the uprated US460 version "continues to use natural 'passive' processes such as convection and gravity," with its modules partially immersed in a below-ground, safety-related pool [6].

Regulation is adapting too. The NRC's 2023 emergency preparedness rule lets SMRs and other new technologies size the plume exposure emergency planning zone using each design's projected doses and accident characteristics, instead of the fixed distance used for large light-water reactors [15]. The rule was published on November 16, 2023 and took effect on December 18, 2023 [15].

Types of SMRs

The IAEA ARIS booklet groups SMR designs into five technology lines [1]:

Type

Coolant

Example

Notes

Water-cooled

Ordinary water

NuScale (U.S.), BWRX-300 (U.S./Canada projects), KLT-40S (Russia)

Closest to today's large light-water reactors

High-temperature gas-cooled

Helium

HTR-PM (China)

High-temperature heat for industry [1]

Liquid metal-cooled fast

Sodium or lead

Natrium (U.S.), BREST-OD-300 (Russia)

Fast neutron spectrum; most advanced designs need HALEU fuel [16]

Molten salt

Molten salts

Various designs in development [1]

Listed by IAEA as a principal technology line [1]

Microreactors

Various

MARVEL research microreactor (U.S. national lab) [1]

Typically up to about 10 MWe [1]

A note on Natrium: its 345 MWe rating, with storage boosting output to 500 MWe [10], is above the IAEA's typical 300 MWe ceiling. It's usually described as an advanced reactor rather than an SMR, but it's relevant here because the NRC calls it the first approval for a non-light-water reactor in more than 40 years [10], and DOE describes it as the first construction permit the NRC has ever issued for a commercial non-light-water power reactor [11]. Natrium is one of two projects in DOE's Advanced Reactor Demonstration Program [11].

Where SMRs stand: key regulatory milestones

Licensing language matters, because a design approval is not a construction permit, and neither is permission to operate. In the U.S., a design certification or standard design approval says a reactor design meets NRC safety requirements; anyone using it still needs permission to build and operate a plant [6]. A construction permit authorizes building at a specific site; a separate operating license is required before loading fuel [8][10].

Date

Milestone

Source

Dec 31, 2016

NuScale files its design certification application with the NRC

[5]

Dec 2019 / May 2020

Russia's floating Akademik Lomonosov (two KLT-40S units) connects to the grid, then begins commercial operation

[1]

Sep 2020

NRC grants the NuScale Power Module a standard design approval, before the 2023 design certification

[1]

Dec 2021

China's HTR-PM demonstrator connects to the grid

[1]

Jan 19, 2023

NRC publishes final rule certifying the NuScale design (12 modules of 50 MWe); effective Feb 21, 2023

[5]

Nov 2023

UAMPS and NuScale terminate the Carbon Free Power Project in Idaho

[13][14]

Nov 16, 2023

NRC publishes emergency preparedness rule for SMRs; effective Dec 18, 2023

[15]

Apr 4, 2025

Canada's CNSC licenses Ontario Power Generation to construct one BWRX-300 at Darlington (licence valid to Mar 31, 2035)

[12]

May 29, 2025

NRC approves NuScale's US460 standard design (six 77 MWe modules, about 460 MWe)

[6][7]

Mar 4, 2026

NRC authorizes its staff to issue a construction permit for TerraPower's Kemmerer Unit 1 (Natrium) in Wyoming; DOE reported the permit issued in a March 9 article

[10][11]

Sep 29, 2026

NRC approves TVA's construction permit for a BWRX-300 at Clinch River, Tennessee, about 14 months after starting its review

[8][9]

Two details stand out. The NuScale US460 approval came "ahead of schedule and under budget," according to the NRC, and two months earlier than its July 2025 target [6][7]. And the TVA permit, which the NRC says clears the way for the nation's first commercial SMR, still leaves TVA needing a separate operating license before it can load fuel [8].

The cautionary tale

The first U.S. project to use a certified SMR design didn't survive. The Carbon Free Power Project, a six-module NuScale plant planned at Idaho National Laboratory by the Utah Associated Municipal Power Systems (UAMPS), was supported by a DOE cost-share award of up to $1.4 billion approved in 2020 and had targeted operation in 2029 [14]. In November 2023 the partners ended it, saying "it appears unlikely that the project will have enough subscription to continue toward deployment" [13]. Not enough utilities signed up to buy the power.

Real-world uses

  • Replacing retiring fossil plants. The IAEA lists "replacing ageing fossil-fired units" among the main drivers of SMR development [1]. TerraPower's Kemmerer site sits near an existing coal-fired power plant [10].
  • Remote and off-grid power. The Akademik Lomonosov floating plant began commercial operation in Pevek, Russia, in May 2020 [1].
  • Industrial heat, hydrogen and desalination. IAEA describes SMRs providing cogeneration for heat, hydrogen production and desalination [1], and DOE lists process heat and desalination among potential uses [2]. For context on how nuclear could feed hydrogen production, see our guide to green hydrogen vs blue hydrogen.
  • Data centers. Technology companies' growing power demand has drawn attention to compact reactors; we've covered one startup's plans in our report on Deep Fission's underground reactors for AI data centers. Treat company timelines in this area as claims until regulators approve specific sites.

Benefits

  • Lower upfront cost per unit. IAEA notes SMRs are "designed for lower upfront capital cost per unit," and DOE cites reduced capital investment [1][2].
  • Siting flexibility. Smaller footprints suit sites that can't host a large plant, including places with limited water [1][3].
  • Incremental capacity. Utilities can add modules as demand grows rather than committing to one very large unit [1][2].
  • Passive safety features that don't depend on external power or pumps [5][6].
  • Firm, low-carbon output that complements variable solar and wind and storage such as battery energy storage systems.

Limitations and risks

  • Unproven economics. The IAEA's own assessment is blunt: SMRs' "economic competitiveness is still to be proven" [1]. Factory savings depend on building many identical units, and none of the U.S. designs has reached that scale. We have not included cost-per-megawatt-hour figures because no U.S. SMR has operating cost data to verify them.
  • Customer commitment. The Carbon Free Power Project failed on subscriptions, not regulation [13][14].
  • Fuel supply. Most advanced, non-light-water designs need high-assay low-enriched uranium (HALEU), enriched to between 5% and 20% uranium-235, while today's U.S. fleet uses fuel enriched to no more than 5% [17]. DOE states that "HALEU is not currently available from domestic suppliers" [16]. Light-water SMRs like NuScale and the BWRX-300 avoid this problem by using conventional fuel.
  • Open technical questions. IAEA lists control-room staffing and human factors for multi-module plants, codes and standards, manufacturing of novel components, and back-end fuel-cycle solutions as issues still drawing attention [1].
  • Waste. SMRs still produce spent nuclear fuel that needs long-term management; IAEA counts back-end fuel-cycle solutions among the open issues [1].
  • Long timelines. NuScale's design certification took about six years from application to effective rule [5], and approved designs still need site-specific construction and operating licenses [6][8].

How to read SMR announcements

  1. Check the licensing stage. Design certification, standard design approval, construction permit and operating license are different things [6][8].
  2. Label dates as company claims unless a regulator has set them. "Operational by 20XX" in a press release is a goal.
  3. Ask about fuel. A design that needs HALEU depends on a supply chain DOE is still building [16].
  4. Look for signed buyers. Offtake agreements and utility ownership matter more than memoranda of understanding, as the Idaho project showed [13].
  5. Check the size. Some "advanced reactors" in SMR headlines exceed the 300 MWe threshold [1][10].

Outlook

In the U.S., the next milestones to watch are construction progress at TVA's Clinch River site and TerraPower's Kemmerer plant, and their eventual operating-license applications [8][10]. In Canada, OPG's Darlington BWRX-300 is licensed to construct but not yet to operate [12].

Internationally, the IAEA's 2022 ARIS booklet listed more than 80 SMR designs across 18 IAEA Member States and recorded targets including commercial operation of China's ACP100 and completion of Russia's BREST-OD-300 by around 2026 [1]. Those were targets as of 2022, not confirmed outcomes; we didn't verify their current status for this article. Our view, rather than any agency's forecast, is that the decisive test is no longer whether regulators will approve SMRs. It's whether the first units can be built on budget and on schedule.

Frequently asked questions

Are any small modular reactors operating today?

Yes, outside the U.S. The IAEA ARIS booklet reports that Russia's floating Akademik Lomonosov plant, with two KLT-40S reactors, began commercial operation in May 2020, and China's HTR-PM demonstrator was connected to the grid in December 2021 [1]. As of November 2026, no commercial SMR is operating in the United States.

How much power does an SMR produce?

Up to about 300 MWe per unit by the IAEA's typical definition [1]. Examples: each NuScale US600 module is rated at 50 MWe [5], each US460 module at 77 MWe [6], and the NRC describes TVA's BWRX-300 as a 300-megawatt reactor [8]. Microreactors are much smaller, typically up to about 10 MWe [1].

Are SMRs safer than traditional reactors?

Many designs rely on passive safety, using natural circulation, convection and gravity instead of powered pumps. NuScale's certified design has no safety-related functions that depend on electrical power [5][6]. Safety is judged design by design through NRC review, so "SMR" alone doesn't guarantee a particular safety level.

What is the difference between an SMR and a microreactor?

Microreactors are a subcategory of SMRs with much smaller output, typically up to about 10 MWe [1]. DOE says most produce 1 to 20 megawatts of thermal energy and are small enough to be transported by truck, ship, aircraft or rail [4].

What fuel do SMRs use?

Light-water SMRs such as NuScale and the BWRX-300 use conventional low-enriched uranium. Many advanced designs need HALEU, enriched to between 5% and 20% uranium-235, which DOE says is not yet available from domestic suppliers [16][17].

When will SMRs supply power to U.S. homes?

No regulator has set a date. TVA and TerraPower hold construction permits but still need operating licenses [8][10]. Any in-service year quoted by a developer should be treated as a company target.

Sources

  1. IAEA Advanced Reactors Information System (ARIS), "Advances in Small Modular Reactor Technology Developments," 2022 Edition (supplement; carries a disclaimer that it is not an official IAEA publication). https://aris.iaea.org/Publications/SMR_booklet_2022.pdf
  2. U.S. Department of Energy, Office of Nuclear Energy, "Advanced Small Modular Reactors (SMRs)." https://www.energy.gov/ne/advanced-small-modular-reactors-smrs
  3. U.S. Department of Energy, Office of Nuclear Energy, "4 Key Benefits of Advanced Small Modular Reactors," May 28, 2020. https://www.energy.gov/ne/articles/4-key-benefits-advanced-small-modular-reactors
  4. U.S. Department of Energy, Office of Nuclear Energy, "What is a Nuclear Microreactor?" February 26, 2021. https://www.energy.gov/ne/articles/what-nuclear-microreactor
  5. U.S. Nuclear Regulatory Commission, "NuScale Small Modular Reactor Design Certification," final rule, Federal Register 88 FR 3287, January 19, 2023. https://www.govinfo.gov/content/pkg/FR-2023-01-19/html/2023-00729.htm
  6. U.S. Nuclear Regulatory Commission, "NRC Approves Standard Design for NuScale US460 Small Modular Reactor," News Release 25-033, May 29, 2025. https://www.nrc.gov/cdn/doc-collection-news/2025/25-033.pdf
  7. U.S. Nuclear Regulatory Commission, "NuScale US460" standard design approval project page. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale-us460
  8. U.S. Nuclear Regulatory Commission, News Release 26-079, September 29, 2026. https://www.nrc.gov/about-nrc/news-releases/2026/26-079
  9. U.S. Nuclear Regulatory Commission, "TVA Clinch River Construction Permit Application" project page. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/advanced-reactor-application-projects/tva-clinch-river-cpa
  10. U.S. Nuclear Regulatory Commission, "NRC Issues First Commercial Reactor Construction Approval in 10 Years for TerraPower in Wyoming," News Release 26-028, March 4, 2026. https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-028.pdf
  11. U.S. Department of Energy, Office of Nuclear Energy, "NRC Issues Construction Permit for TerraPower's Natrium Advanced Reactor," March 9, 2026. https://www.energy.gov/ne/articles/nrc-issues-construction-permit-terrapowers-natrium-advanced-reactor
  12. Canadian Nuclear Safety Commission, "Commission authorizes Ontario Power Generation Inc. to construct 1 BWRX-300 reactor at the Darlington New Nuclear Project site," April 4, 2025. https://www.canada.ca/en/nuclear-safety-commission/news/2025/04/commission-authorizes-ontario-power-generation-inc-to-construct-1-bwrx-300-reactor-at-the-darlington-new-nuclear-project-site.html
  13. UAMPS and NuScale Power, "UAMPS and NuScale Power Agree to Terminate the Carbon Free Power Project (CFPP)," joint press release filed with the U.S. SEC, November 2023. https://www.sec.gov/Archives/edgar/data/1822966/000182296623000256/uampsnuscalejointpressre.htm
  14. World Nuclear News, "Idaho SMR project terminated," November 9, 2023. https://wnn.world-nuclear.org/articles/idaho-smr-project-terminated
  15. U.S. Nuclear Regulatory Commission, "Emergency Preparedness for Small Modular Reactors and Other New Technologies," final rule, Federal Register 88 FR 80050, November 16, 2023. https://www.govinfo.gov/content/pkg/FR-2023-11-16/html/2023-25163.htm
  16. U.S. Department of Energy, Office of Nuclear Energy, "HALEU Availability Program." https://www.energy.gov/ne/haleu-availability-program
  17. U.S. Department of Energy, Office of Nuclear Energy, "HALEU Frequently Asked Questions." https://www.energy.gov/ne/haleu-frequently-asked-questions