LIVEยทThe trends shaping tomorrow's world.
Green Tech

Offshore vs Onshore Wind Energy: How They Compare

Offshore vs onshore wind compared: turbine size, foundations, capacity factors, costs, transmission and US policy fights, with data as of Nov 2026.

Onshore wind turbines stand on land. Offshore turbines stand in the sea, on foundations fixed to the seabed or on floating platforms. Offshore sites usually have stronger, steadier winds and room for much bigger turbines, but they cost more to build, connect and maintain. In the US, onshore wind is a mature, large-scale resource: wind supplied about 11% of utility-scale electricity in 2025, nearly all of it onshore [1][2]. Offshore wind is just getting started: its first two large projects, Vineyard Wind 1 and Revolution Wind, reached full operation only in late 2026, after years of delays and federal policy fights [7][8].

How the two compare at a glance

Factor

Onshore wind

Offshore wind

Typical new turbine size (US)

About 3.5 MW average in 2024 [3]

Much larger; Vineyard Wind's 62 turbines total about 800 MW, or roughly 13 MW each [7]

Foundations

Concrete foundation on land

Fixed-bottom (monopiles, jackets) in shallow water; floating platforms in deep water [4]

Wind resource

Varies widely by site

Generally stronger and more consistent over open water [5][7]

Construction

Roads, cranes, local labor

Specialized ships, ports, marine weather windows

Transmission

Often needs long lines from rural sites to cities

Subsea export cables to the coast, closer to coastal demand centers

US maturity (as of Nov 2026)

Mature, large fleet

Few operating projects; others under construction or stalled [2][7][8]

Main risks

Siting, local opposition, transmission

Cost, supply chain, vessels, permitting and policy reversals

Turbines: why offshore goes bigger

A turbine's power output rises steeply with wind speed and with the area its blades sweep. Bigger rotors in stronger wind produce far more energy.

On land, size is limited by transport. Blades and tower sections have to travel by road and rail. DOE notes that offshore turbines "do not have the same transportation challenges" because components move by ship. Offshore turbines are often taller than the Statue of Liberty [5].

The numbers show the gap. New US land-based turbines installed in 2024 averaged 3.5 MW, with a 106-meter hub height and a 137-meter rotor diameter, according to Berkeley Lab [3]. Offshore, Vineyard Wind's 62 turbines can generate about 800 MW in total [7], which works out to roughly 13 MW per turbine.

For the mechanics of how a turbine turns wind into electricity, see wind energy technology explained.

Foundations: fixed-bottom vs floating

How an offshore turbine is held in place depends on water depth. The national lab behind the Annual Technology Baseline (the National Laboratory of the Rockies, formerly NREL) assigns sites shallower than 60 meters to fixed-bottom technology and deeper sites to floating technology [4].

  • Fixed-bottom foundations, such as steel monopiles driven into the seabed or lattice jackets, suit the relatively shallow waters off the US Northeast. That's where the early US projects are.
  • Floating platforms are moored to the seabed with lines and anchors. They open up deep-water areas like the US Pacific coast. The 2025 ATB presents floating offshore wind costs from 2030 onward, when the first commercial-scale US floating projects "could feasibly come online" [4].

The national lab estimates the US offshore technical resource "likely exceeds 2,000 gigawatts" after excluding areas for depth limits, shipping lanes, protected areas and other uses [4].

Output: capacity factors

Capacity factor measures actual output against running at full power all year.

  • Onshore: US wind (overwhelmingly onshore) averaged a 33.8% capacity factor in 2025 [9]. Newer projects do better: projects built in 2023 averaged 37.5% in 2024, compared with 34% for the 1998โ€“2023 fleet, according to Berkeley Lab [3]. Berkeley Lab notes that lower specific power, meaning a bigger rotor relative to the generator's rating, leads to higher capacity factors [3].
  • Offshore: Strong, consistent ocean winds are the main reason to go offshore [5][7]. The US has too little operating history for a meaningful national average yet. Vineyard Wind, for example, finished construction in mid-March 2026 but reached full commercial operation only on October 29, 2026 [7].

Costs

Onshore wind is relatively inexpensive to build and run at good sites. Installed costs for US land-based projects averaged $1,850/kW in 2024 [3]. Berkeley Lab estimates the levelized cost of energy for land-based wind plants built in 2023 and 2024 ranged from $40/MWh in ERCOT (Texas) to $67/MWh in NYISO (New York), excluding the production tax credit [3].

Offshore wind costs far more to build because of marine construction, foundations, subsea cables, specialized vessels, port upgrades and harder maintenance. Vineyard Wind 1 cost about $4.5 billion for 800 MW [7], roughly $5,600 per kW. Higher output per turbine offsets part of that. The ATB models offshore costs by site, based on wind resource, water depth and distance to infrastructure [4].

Where each fits in the US

  • Onshore wind is concentrated in the middle of the country. In 2025, Texas, Iowa, Oklahoma, Kansas and Illinois together produced about 52% of US wind electricity [2]. Big projects keep coming: as of February 2026, EIA expected the 3,650-MW SunZia Wind project in New Mexico to start commercial operation in 2026 as the largest onshore wind project in the US [6].
  • Offshore wind targets the coasts, especially the Northeast. That region has few other large clean-power options. The six New England states have no oil or gas reserves and limited open land for renewables, while their shallow coastal waters have some of the strongest and most consistent winds in the world, according to WBUR [7].

US offshore wind: status and policy (as of November 2026)

US offshore wind has been shaped as much by policy as by engineering:

  • Operating projects. At the end of 2024, the US had two operating offshore wind projects: South Fork Wind (130 MW) off New York and the partly built Vineyard Wind 1 (174 MW at the time) [2]. Vineyard Wind 1 reached full commercial operation on October 29, 2026, with 62 turbines and about 800 MW. Revolution Wind (704 MW) announced it had reached full power just before that [7].
  • Federal pauses. On December 22, 2025, the Interior Department paused leases for five large offshore wind projects under construction, citing national security risks identified by the Pentagon, including radar "clutter" from turbines [8]. They were Vineyard Wind, Revolution Wind, Coastal Virginia Offshore Wind, Sunrise Wind and Empire Wind. Two weeks earlier, a federal judge in Massachusetts had vacated the administration's January 20, 2025 order halting wind leasing and permitting, calling it "arbitrary and capricious" [8]. Several federal judges later ruled against the December pauses, and the projects were allowed to resume work [7].
  • Permitting freeze. As of November 2026, WBUR reports that a blanket federal permitting pause has effectively frozen progress on all but the five projects already under construction [7].
  • Pipeline. As of May 2026, developers reported plans for about 5,089 MW of offshore wind capacity off New York, Rhode Island and Virginia, according to EIA [2].

Given how often these decisions change, check the latest status of any specific project before relying on it.

Benefits and drawbacks

Onshore wind

  • Pros: lower cost, mature supply chain, faster construction, can share land with farming.
  • Cons: visual and noise concerns near homes, wildlife impacts, long transmission lines from windy rural areas.

Offshore wind

  • Pros: stronger, steadier winds; huge turbines; close to coastal cities; vast technical potential [4][5][7].
  • Cons: higher costs, need for specialized ports and vessels, conflicts with fishing and navigation, and exposure to permitting and policy reversals [8].

How to think about the choice

Utilities and states don't really choose one or the other. They choose based on geography:

  1. Is there good land with wind and transmission access? Onshore usually wins on cost [3].
  2. Is land scarce and demand coastal? Offshore may be the main large-scale option, as in New England [7].
  3. How deep is the water? Shallow water (under about 60 m) allows fixed-bottom turbines. Deeper water needs floating technology that's still maturing [4].
  4. How much policy risk can the project carry? Recent US offshore experience shows that permits and leases can be paused after construction starts [8].

Outlook

Expect US wind additions to recover in 2026: as of February 2026, EIA counted 11.8 GW of onshore and offshore wind planned for the year, more than double the 2025 total [6]. US offshore wind's near-term future depends on how the paused projects and court cases resolve. Floating offshore wind is a longer-term prospect for the 2030s [4]. Pairing wind with storage and stronger grids helps manage its variability. See grid-scale energy storage and smart grid technology.

Frequently asked questions

Is offshore wind better than onshore wind?

Neither is better everywhere. Offshore sites usually have stronger, steadier winds and allow larger turbines [5][7], but they cost more to build and maintain. Onshore wind is cheaper at good sites [3].

Why are offshore wind turbines so much bigger?

Their parts travel by ship instead of road, so size isn't limited by highway transport [5]. New US onshore turbines averaged 3.5 MW in 2024 [3]. Vineyard Wind's offshore turbines average roughly 13 MW each (about 800 MW from 62 turbines) [7].

How much US electricity comes from wind?

About 11% of US utility-scale generation in 2025, almost all from onshore turbines [1]. Texas, Iowa, Oklahoma, Kansas and Illinois produce about half of it [2].

What is floating offshore wind?

Turbines mounted on buoyant platforms moored to the seabed, used where water is too deep for fixed foundations. The national lab uses 60 meters as the cutoff [4]. The lab's cost baseline for floating wind starts in 2030, when the first commercial-scale US floating projects could feasibly come online [4].

What happened to US offshore wind projects in 2025?

In December 2025, the Interior Department paused leases for five East Coast projects under construction, citing national security concerns [8]. Two of them, Vineyard Wind 1 and Revolution Wind, reached full operation in late 2026 [7].

Sources

  1. U.S. Energy Information Administration. "Electricity explained: Electricity in the United States." https://www.eia.gov/energyexplained/electricity/electricity-in-the-us.php
  2. U.S. Energy Information Administration. "Wind explained: Where wind power is harnessed." https://www.eia.gov/energyexplained/wind/where-wind-power-is-harnessed.php
  3. Lawrence Berkeley National Laboratory. "Land-Based Wind Energy Technology Update: 2025 Edition." Figure file, August 2025. https://emp.lbl.gov/sites/default/files/2025-08/FIGURE%20FILE_Land-Based%20Wind%20Energy%20Technology%20Update_2025%20Edition.pdf
  4. National Laboratory of the Rockies (formerly NREL). "Annual Technology Baseline 2025: Offshore Wind." https://atb.nlr.gov/electricity/2025/offshore_wind
  5. U.S. Department of Energy, Wind Energy Technologies Office. "How Do Wind Turbines Work?" https://www.energy.gov/eere/wind/how-do-wind-turbines-work
  6. U.S. Energy Information Administration. "New U.S. electric generating capacity expected to reach a record high in 2026." Today in Energy, February 20, 2026. https://www.eia.gov/todayinenergy/detail.php?id=67205
  7. Wasser, M. "Vineyard Wind, the country's largest offshore wind project, is fully up and running." WBUR, November 6, 2026. https://wbur.org/news/2026/11/06/vineyard-wind-fully-running-offshore-wind-massachusetts
  8. NPR / Associated Press. "The Trump administration pauses wind projects off New England, New York and Virginia." December 22, 2025. https://www.npr.org/2025/12/22/g-s1-103320/offshore-wind-power-pause-trump-administration-new-england-new-york-virginia-national-security
  9. U.S. Energy Information Administration. "Electric Power Annual, Table 4.08.B." Data for 2025. https://www.eia.gov/electricity/annual/html/epa_04_08_b.html